Deemed to be included update

Taking off top tip 12 pointed out
the recommended approach to account items that are deemed to be included items according to the RICS Guidelines on NRM 2: Detailed measurement of building works.
The guidelines go on to say;
Where the rules state that an item of work is deemed
included but this work is of particularly high value either by material content or location, the QS should measure the work, clearly stating the departure from the rules.